Sanction
No.-DRDA-CBA-(NREGA)/2008-07- 1410-16 |
Dated:-
26/06/2009 |
|
Total No
of Schemes:
190 |
Amount |
47380000 |
|
Sr.No. |
Name of Scheme |
Gram Panchayat |
Amount
Sanctioned |
|
1 |
C/O
Irrigation Tank Village Chaloga |
Athluin |
70000 |
|
|
Total |
|
70000 |
|
1 |
C/O Kachha
Rasta/Soil conservation work at Jamuhar to
Seri (ZP) |
Baat |
100000 |
|
2 |
C/O Link
Road Devi faati to Upper Panela |
Baat |
600000 |
|
3 |
C/O Link
Road from Kholi to Lower Niyan |
Baat |
600000 |
|
4 |
Creat Work
Panela, Jeenu, Sandooh |
Baat |
600000 |
|
5 |
C/O
PaccaPath Agahar to Malla |
Baat |
600000 |
|
|
Total |
|
2500000 |
|
1 |
C/O Pacca
Path Khapras to Chunda Tank |
Bailly |
200000 |
|
2 |
C/O Link
RoadKhapra, Chuda |
Bailly |
200000 |
|
3 |
C/O
Panihar village Lunehed |
Baily |
100000 |
|
4 |
C/O Pacca
Rasta Kadpei to Goth |
Baily |
600000 |
|
5 |
C/O Land
Development Work at Khapra |
Baily |
600000 |
|
6 |
C/O Link
road at Karapdei Badi Jamuhar |
Baily |
900000 |
|
|
Total |
|
2600000 |
|
1 |
C/O Land
Dev. /Plantation work Sh. Dharam SinghS/O Sh.
Pinju Ram vill. Bakan SC/IRDP |
Bakan |
25000 |
|
2 |
C/O Pucca
Path vill .Kalwada to Drabbad |
Bakan |
100000 |
|
3 |
C/O Water
Stroage Tank vill Bakan |
Bakan |
70000 |
|
|
Total |
|
195000 |
|
1 |
C/O Land
Protection work village Kuthlu Bhanera (BPL
family) |
Bakatpur |
150000 |
|
2 |
C/O Pucca
path Dipu Chuliara Goth to main road
Khajjiar |
Bakatpur |
300000 |
|
3 |
C/O Land
protection work vill. Falota (ST & BPL
family) |
Bakatpur |
150000 |
|
4 |
C/O Land
protection work & Dry Nahar vill. Padhrotu
(ST & BPL family) |
Bakatpur |
150000 |
|
5 |
C/O Pucca
path Falota to Bakatpur |
Bakatpur |
300000 |
|
6 |
C/O Land
protection work vill. Dharmari (Bandbehi) |
Bakatpur |
200000 |
|
7 |
C/O Land
protection work vill. Banasati (Sonthal)
(ST& BPL family) |
Bakatpur |
150000 |
|
8 |
C/O Crate
work vill. Badhan (ST & BPL family) |
Bakatpur |
150000 |
|
9 |
C/O
Panihar vill. Nichli Badhan |
Bakatpur |
50000 |
|
10 |
C/O Land
Protection work vill. Ghared (Bakatpur)
Ganesh |
Bakatpur |
100000 |
|
|
Total |
|
1700000 |
|
1 |
C/O
Proection work Kalongs |
Baloth |
500000 |
|
|
Total |
|
500000 |
|
1 |
C/O Irri.
Tank Bandla |
Bandla |
70000 |
|
2 |
C/O Soil
Protection work at village Lower Mahled (ZP) |
Bandla |
300000 |
|
|
Total |
|
370000 |
|
1 |
C/O Crate
work vill. Badhwala nalla |
Basodhan |
200000 |
|
2 |
C/O Land
Protection work Upper Bhuin (ST & BPL
family) |
Basodhan |
70000 |
|
3 |
C/O
Protection work Nichli Bhuin |
Basodhan |
100000 |
|
4 |
C/O
Irrigation Tank vill. Padeda (ST& BPL
family) |
Basodhan |
200000 |
|
5 |
C/O Land
protection work vill. Bangotu (ST & BPL
family) |
Basodhan |
200000 |
|
6 |
C/O
Irrigation Tank village Mankot (ST family) |
Basodhan |
200000 |
|
|
Total |
|
970000 |
|
1 |
C/O
Panihar village Diyoli |
Bhadian |
50000 |
|
2 |
C/O Crate
work Notod |
Bhadian |
100000 |
|
3 |
C/O Crate
work Tendha to Manidir |
Bhadian |
100000 |
|
4 |
C/O
Irrigation Tank Janot |
Bhadian |
300000 |
|
5 |
C/O Land
Proctection work vill. Upper Mukleni |
Bhadian |
100000 |
|
6 |
C/O Land
Proctection work vill. Nichli Mukleni |
Bhadian |
500000 |
|
7 |
C/O Lanb
Proection work vill. Jahed |
Bhadian |
100000 |
|
8 |
C/O Check
dam upper Thed |
Bhadian |
100000 |
|
9 |
C/O Soil
Conservation work at Dodan to Jatehad (ZP) |
Bhadiyan |
200000 |
|
10 |
C/O Soil
conservation work at village Marda (ZP) |
Bhadiyan |
150000 |
|
11 |
C/O Road
at Marda to Shamshan Ghat (ZP) |
Bhadiyan |
100000 |
|
|
Total |
|
1800000 |
|
1 |
C/O Soil
Conservation work at Androur to Tappar (ZP) |
Brehi |
200000 |
|
2 |
C/O Soil
Conservation work at Androur to Ghatta (ZP) |
Brehi |
200000 |
|
3 |
C/O Check
dam / Plantation Banehet ar Nalla |
Brehi |
100000 |
|
4 |
C/O Wator
Stroage Tank vill Mehla |
Brehi |
50000 |
|
5 |
C/O Land
Development Chundrika vill Tur |
Brehi |
50000 |
|
6 |
C/O Crate
work Tapper Nali Banei |
Brehi |
50000 |
|
7 |
C/O Land
Dev. Sh. Gungar Mal S/O Sh Sekhu vill Drbri
(SC/IRDP) |
Brehi |
15000 |
|
8 |
C/O Land
Dev. Sh. Suneet S/O Sh Sorma vill Dudhwara
(SC/BPL) |
Brehi |
20000 |
|
9 |
C/O Wator
Stroage Tank vill Banei (SC/BPL) |
Brehi |
25000 |
|
10 |
C/O Land
Dev. Work Sh Karma Chand S/O SH Hosiyara
Vill. Batnu SC/IRDP |
Brehi |
20000 |
|
11 |
C/O Land
Dev. Work Smt. Krishan vill Kungad Vill.
Kunged ST/IRDP |
Brehi |
20000 |
|
12 |
C/O Land
Dev. Work Sh. Raj Kumar S/O Sh. Hari Chand
vill.Tur SC/IRDP |
Brehi |
20000 |
|
13 |
C/O Land
Dev. Work Sh. Kalyan Singh S/O Sh. Banku
Ram vill.Tur SC/IRDP |
Brehi |
15000 |
|
14 |
C/O Check
dam /Flood Proection Jillo BatogadiThutelil
vill Tur |
Brehi |
100000 |
|
15 |
C/O Land
Dev. Work Smt. Hallu w/oSh Mukholil vill Tur
SC/IRDP) |
Brehi |
25000 |
|
16 |
C/O Check
Dak Nali near Gadiyara |
Brehi |
50000 |
|
17 |
C/O Play
ground GMS Tur |
Brehi |
150000 |
|
18 |
C/O Play
ground vill. Banei |
Brehi |
80000 |
|
19 |
C/O Play
Ground Sukral |
Brehi |
80000 |
|
20 |
C/O Play
Ground vill Tur |
Brehi |
100000 |
|
21 |
C/O Pucca
Path Dibbri to vill. Ghatt |
Brehi |
100000 |
|
22 |
C/O Water
Stroges Tank vill. Kuged |
Brehi |
50000 |
|
23 |
C/O Water
Stroages Tank Kuthwada |
Brehi |
70000 |
|
24 |
C/O Water
Stroage Tank Chaloon to Phatti |
Brehi |
70000 |
|
|
Total |
|
1660000 |
|
1 |
C/O
Panihara at Urilla |
Chadi |
25000 |
|
|
Total |
|
25000 |
|
1 |
C/O Irri.
Tank Chhatradi |
Chhatradi |
70000 |
|
|
Total |
|
70000 |
|
1 |
C/O Flood
Proection Dromed Khad to Dughod |
Darwain |
700000 |
|
2 |
C/O Crate
work upper Behdora |
Darwain |
30000 |
|
3 |
C/O Pucca
path Jeedu to Gule nal |
Darwain |
50000 |
|
4 |
C/O Irri.
Tank vill. Jeedu |
Darwain |
40000 |
|
5 |
C/O Water
Stroges Tank Darwin |
Darwain |
50000 |
|
6 |
C/O Land
Dev. Work Sh. Makholi Ram vill. Jeedu(IRDP) |
Darwain |
20000 |
|
|
Total |
|
890000 |
|
1 |
C/O Land
Development Work at Sambra |
Dhulara |
600000 |
|
|
Total |
|
600000 |
|
1 |
C/O
Irrigation tank Village Gagla |
Gagla |
100000 |
|
|
Total |
|
100000 |
|
1 |
C/O Irri.
Tank v ill. Madhara Drabad |
Gehra |
50000 |
|
2 |
C/O Tank
(Vegetable) Gehra Sh. Ravinder Kumar(SC/IRDP)
Patpadi |
Gehra |
40000 |
|
3 |
C/O Flood
Proection Gehra Nala |
Gehra |
80000 |
|
4 |
C/O Water
Stroage Tank vill. Lohrada |
Gehra |
60000 |
|
|
Total |
|
230000 |
|
1 |
C/O of
Ponds Baddi Jamuhar |
Gowad |
100000 |
|
2 |
C/O Link
Road Sari to Sobei. |
Gowad |
500000 |
|
3 |
C/O Link
Road Sahluin to GMS Bhala |
Gowad |
600000 |
|
4 |
C/O Link
Road Ganji to Thaneta |
Gowad |
300000 |
|
5 |
C/O Pacca
Rasta/sukhi nehar Kilot to sella |
Gowad |
600000 |
|
6 |
C?O Dry
Nehar at village Shaglamadhikot |
Gowad |
200000 |
|
7 |
C/O Dry
Nehar Guwad, Bhala Siyuni Jajred |
Gowad |
800000 |
|
|
Total |
|
3100000 |
|
1 |
C/O Land
Development Work at Village Gurad |
Gurad |
600000 |
|
2 |
C/O
Protection work at village Bhalei (BPL/ST
Family) |
Gurad |
100000 |
|
3 |
C/O
Irrig.Tank Bhalei. |
Gurad |
150000 |
|
|
Total |
|
7050000 |
|
1 |
C/O Land
Development Work at village futti Saraina |
Jangi |
600000 |
|
|
Total |
|
600000 |
|
1 |
C/O Land
Protection work vill. Jatkari |
Jatkari |
100000 |
|
2 |
C/O
Irrigation tank village Khawahda |
Jatkari |
100000 |
|
3 |
C/O Crate
work village Jatehd Nalla |
Jatkari |
200000 |
|
4 |
C/O
Panihar village Hured |
Jatkari |
50000 |
|
5 |
C/O Crate
work at village Tikkar(ST/BPL Family) |
Jatkari |
300000 |
|
|
Total |
|
750000 |
|
1 |
C/O
Proection work Almi |
Khundel |
500000 |
|
|
Total |
|
500000 |
|
1 |
C/O
Irrigation Tank village Sharol |
Kidi |
80000 |
|
2 |
C/O
Irrigation Tank village Mangrol |
Kidi |
80000 |
|
3 |
C/O Dry
Nehar at village Madolu |
Kidi |
100000 |
|
4 |
C/O Dry
Nehar at Padhrui Ossal |
Kidi |
200000 |
|
|
Total |
|
460000 |
|
1 |
C/O Dry
Canal Kalmala to Matena |
Kilod |
500000 |
|
|
Total |
|
500000 |
|
1 |
C/O Land
proection vill. Kuthla (ST)(BPL)Family |
Kolka |
200000 |
|
2 |
C/O
Irrigation Tank Vill. Umal Kalei (Dharmari) |
Kolka |
150000 |
|
3 |
C/O Land
Proection vill. Dhamgran (ST)(BPL)Family |
Kolka |
100000 |
|
4 |
C/O Land
Proection vill. Priyungal(ST)(BPL)Family |
Kolka |
150000 |
|
5 |
C/O Pucca
path vill. Priyungal to Nichla Pundla |
Kolka |
150000 |
|
6 |
C/O Pucca
path vill. Priyungal toMukleni |
Kolka |
150000 |
|
7 |
C/O Land
Proection work Nichla Bhalka(ST)(BPL)Family |
Kolka |
150000 |
|
8 |
C/O Dry
Canal v ill . Matana to Kolka(ST)(BPL)Family |
Kolka |
200000 |
|
9 |
C/O Land
Proection work vill. Kaloti(ST)(BPL)Family |
Kolka |
100000 |
|
10 |
C/O Land
Proection work vill. Upper Kunda to
Khilla(ST)(BPL)Family |
Kolka |
100000 |
|
|
Total |
|
1450000 |
|
1 |
C/O
Proection work vill. Gothuru |
Kuned |
200000 |
|
2 |
C/O
Proection work near vill. Bandla |
Kuned |
300000 |
|
|
Total |
|
500000 |
|
1 |
C/O Irri.
Tank vill. Jantra |
Kunr |
50000 |
|
2 |
C/O Flood
Proection vill. Behi |
Kunr |
50000 |
|
3 |
C/O Land
Dev. Sh. Happa and Nanak Chand Kunr SC/BPL
family |
Kunr |
20000 |
|
|
Total |
|
120000 |
|
1 |
C/O Jeep
road main road to Khilla |
Kupahada |
600000 |
|
2 |
C/O Land
Proection work vill. Naled (ST & BPL family) |
Kupahada |
100000 |
|
3 |
C/O Pucca
path Bharmani nala to Kuthed Mandir |
Kupahada |
150000 |
|
|
Total |
|
850000 |
|
1 |
C/O Play
ground Jadoli |
Lothal |
100000 |
|
2 |
C/O Play
ground Marotha |
Lothal |
80000 |
|
3 |
C/O Water
Stroges Tank Bahog |
Lothal |
50000 |
|
4 |
C/O Water
Stroage Tank vill. Dharwala |
Lothal |
30000 |
|
5 |
C/O Water
Stroage Tank vill. Guwad |
Lothal |
50000 |
|
6 |
C/O Pucca
path Sakak to Bahog vill. |
Lothal |
100000 |
|
7 |
C/O Water
Stroage Tank Vill. Chudi |
Lothal |
100000 |
|
8 |
C/O Soil
Conservation workat Lothal to Luharka (ZP) |
Lothal |
100000 |
|
9 |
C/O Water
Stroge Tank vill. Martha |
Lothal |
50000 |
|
10 |
C/O Flood
Proection /Check dam Luharka nala |
Lothal |
100000 |
|
11 |
C/O Check
dam /Planation work Jadoli nala |
Lothal |
100000 |
|
12 |
C/O Land
Dev.Sh. Sham lal S/O Sh. Dhiya vill. Marotha
BPL family |
Lothal |
25000 |
|
13 |
C/O Irri
.Tank Kuk Marotha |
Lothal |
35000 |
|
14 |
C/O Land
Dev. Sh. Munshi Ram S/O sh Nihal vill.
Luharka family SC/IRDP |
Lothal |
20000 |
|
15 |
C/O Land
Dev. Sh. Dhari Ram S/O Sh. Soji vill Jadoli
family SC/IRDP |
Lothal |
20000 |
|
16 |
C/O Fruit
Plantation under Dharbala Pull ka Niche |
Lothal |
25000 |
|
17 |
C/O Land
Dev. Smt. Punni Widow Sh. Tlochandahog
family SC/IRDP |
Lothal |
20000 |
|
18 |
C/O Land
Dev. Vill Jadoli |
Lothal |
50000 |
|
19 |
C/O Pully
Marathi nali |
Lothal |
100000 |
|
20 |
C/O Land
Development work at Roshan Lal S/O Sh.Jagdev
SC/IRDP vill. Jadoli |
Lothal |
20000 |
|
|
Total |
|
1175000 |
|
1 |
C/O
Proection work vill. Guwad |
Lech |
500000 |
|
|
Total |
|
500000 |
|
1 |
C/O Pacca
Path Khalani Nalla to Ghaloli |
Luddu |
100000 |
|
2 |
C/O Land
Development work at Luddu |
Luddu |
200000 |
|
3 |
C/O Dry
Nehar at village Chakla |
Luddu |
200000 |
|
|
Total |
|
500000 |
|
1 |
C/O Jeep
road main road Hada to Bharodi Apla |
Mangla |
500000 |
|
2 |
C/O Pucca
Path Ghar to Dumama via Chaneli |
Mangla |
300000 |
|
3 |
C/O
Irrigation tank Drabla |
Mangla |
200000 |
|
|
Total |
|
1000000 |
|
1 |
C/O Irri.
Tank vill .Rukhwada Piyura |
Piyura |
50000 |
|
2 |
C/O Pucca
Path vill. Batti to Hatti Bhador |
Piyura |
150000 |
|
|
Total |
|
200000 |
|
1 |
C/O Land
Proection work Gawad-II (SC,ST) |
Preena |
500000 |
|
|
Total |
|
500000 |
|
1 |
C/O
Proection work vill. Kudden |
Radi |
500000 |
|
2 |
C/O Check
dam Gangodi |
Radi |
300000 |
|
3 |
C/O
Plantation work and proection work Nonot |
Radi |
200000 |
|
4 |
C/O Crate
work Dibba |
Radi |
300000 |
|
5 |
C/O
Jeepable road main road vill. Gandhak |
Radi |
800000 |
|
6 |
C/O Check
dam Kui Nali |
Radi |
200000 |
|
7 |
C/O
Proection work Kudden |
Radi |
200000 |
|
8 |
C/O
Proection Guwad |
Radi |
200000 |
|
|
Total |
|
2700000 |
|
1 |
C/O Soil
Conservation work at village Behi near
Anganbari Bhavan Gudda (ZP) |
Rajera |
150000 |
|
2 |
C/O Land
Development at Village Sanged Kuphadu |
Rajera |
600000 |
|
3 |
C/O Land
Development Work at Thalla |
Rajera |
600000 |
|
4 |
C/O
Protection Work at Bhatwara |
Rajera |
100000 |
|
5 |
C/O
Protection Work at Danala Ghar |
Rajera |
100000 |
|
|
Total |
|
1550000 |
|
1 |
C/O Land
Protection work vill. Upper Miadi (ST & BPL
family) |
Rathiar |
100000 |
|
2 |
C/O Crate
work Runheli (Saun) |
Rathiar |
100000 |
|
3 |
C/O Land
Protection work upper Talai |
Rathiar |
100000 |
|
|
Total |
|
300000 |
|
1 |
C/O Link
Road from kudeen to Drobi |
Sarahan |
2000000 |
|
2 |
C/O Link
Road Jhaleni to Raan |
Sarahan |
1500000 |
|
3 |
C/O Pacca
Rasta drobi to village Bahrei, Chalat |
Sarahan |
800000 |
|
4 |
C/O Dry
Cannal Uppar Chulla kuled |
Sarahan |
500000 |
|
5 |
C/O Pacca
Rasta Ghatred to Upper Bhun |
Sarahan |
300000 |
|
6 |
C/O Link
Road Galu Nala to Upper Maloh |
Sarahan |
200000 |
|
7 |
C/O Pacca
Path Mandhruin to Lower Meloh |
Sarahan |
100000 |
|
8 |
C/O of
Culvert Kaluni Dadar Nalla. |
Sarahan |
200000 |
|
9 |
C/O Dry
Nehar Jhikkru Ukhali Maloh |
Sarahan |
300000 |
|
|
Total |
|
5900000 |
|
1 |
C/O Water
Stroge Tank vill. Rondi |
Sunara |
40000 |
|
2 |
C/O Check
dam Khil nala to Dhidho nala |
Sunara |
100000 |
|
3 |
C/O Check
dam Bagga nala |
Sunara |
25000 |
|
4 |
C/O Check
dam / Plantation work Darobi nala |
Sunara |
100000 |
|
5 |
C/O Pucca
Path Guwan to Nichli Karnali |
Sunara |
80000 |
|
6 |
C/O Check
Dam Tatur nalla |
Sunara |
50000 |
|
7 |
C/O Pucca
Path Mukanatha to Panahir |
Sunara |
50000 |
|
|
Total |
|
445000 |
|
1 |
C/O Link
road Dehra to Primary School Kumahrka |
Uteep |
1000000 |
|
2 |
C/O Soil
Conservation at village Kakiyan Main Road |
Uteep |
150000 |
|
3 |
C/O Pacca
Rasta Main road to Upper Saluin |
Uteep |
200000 |
|
4 |
C/O Soil
conservation/ Water harvesting at Bharaini |
Uteep |
50000 |
|
5 |
C/O Link
Road Badi Dehra to Dhudu Mandir,Bhujja. |
Uteep |
1000000 |
|
6 |
C/O Pacca
Path Main Road to Shamshan Ghat (Power
House) |
Uteep |
50000 |
|
|
Total |
|
2450000 |
|
190 |
Grand Total |
|
47380000 |
|
|
(Rs. Four
crore seventy three lacs eighty thousand
only) |